Phoenix STS Logo
Articles

When the Power Fails: Winter Fire Safety and Evacuation Readiness in Nursing Homes

Author

Paddy McDonnell

Date Published

Blue enclosed diesel generator on a skid base beside a paved area and trees.

A nursing home's winter contingency plan should explain how residents will remain safe when the normal electricity supply is interrupted. Management needs evidence of which fire-safety systems and essential equipment remain available, how those arrangements will be sustained and what staff will do if conditions deteriorate.

The presence of a generator does not answer all of those questions. Nor does a successful fire drill establish that staff can manage a prolonged outage affecting equipment, communications and access to the building. The arrangements need to be considered together, against the needs of the residents who are actually living in the centre.

The HSE's Severe Weather Planning Guidance for HSE Services, September 2026, provides a timely basis for reviewing disruption to essential services. Its organisational instructions apply to HSE services. Private nursing-home providers can use relevant planning principles alongside their own legal duties, clinical arrangements and site-specific fire strategy.

Is a power failure the same as a fire emergency?

A power failure without fire requires an assessment of the services and safeguards still available. There may be no immediate reason to move residents, provided their needs can continue to be met safely. Equally, remaining in the building cannot be justified simply because the fire alarm has not activated.

An actual fire requires the centre's fire procedures to be implemented promptly. Staff should not wait for electricity to return before raising the alarm, calling for assistance or carrying out the actions required by those procedures.

Progressive horizontal evacuation is a fire strategy involving movement between suitable compartments or sub-compartments. It should not be presented as the automatic response to a building-wide electrical outage. The HIQA Fire Safety Handbook describes evacuation arrangements in relation to the building, residents and available staff. Moving a resident to the next compartment may provide protection from fire, but it does not necessarily restore the electricity or care facilities they need.

The distinction should be clear in training. Staff need to recognise when they are managing an interruption to services, when a fire-safety system is impaired and when an immediate emergency response is required.

What do the Irish regulations require?

The 2013 care and welfare regulations for designated centres for older people, as amended, provide the relevant framework. Regulation 4 and Schedule 5 require written policies and procedures covering risk management, emergencies and fire safety management.

Regulation 26(2) requires a plan for major incidents likely to cause death or injury, serious disruption to essential services or property damage. Regulation 28 addresses fire precautions, maintenance, staff training and evacuation where necessary, including safe placement of residents. Regulation 15 links staffing numbers and skill mix to the assessed needs of residents and the centre's size and layout.

These provisions establish duties. The planning questions below are practical recommendations for applying them to electrical disruption; they are not additional statutory requirements or a substitute for a site-specific assessment.

Which systems will continue to work?

Management should arrange a review with the people responsible for the electrical installation, fire-safety systems, equipment and care delivery. The useful output is a clear account of what staff can rely on when the normal supply is lost.

For each relevant system, establish its normal supply, any alternative supply, what happens during changeover and the evidence supporting continued operation. Record the person responsible for resolving uncertainty. A list of equipment names alone will not explain the consequences for residents.

The review should cover:

  • Fire detection and warning. Identify the supply arrangements and any relevant faults, monitoring connections or interfaces. Confirm what staff must do if normal indication, signalling or associated functions become unavailable.
  • Emergency lighting and escape routes. Establish which areas are covered, the maintenance and test evidence, and how staff will recognise and report a failure. Include the route to any external place of safety.
  • Doors and access controls. Check the intended response of hold-open devices, powered doors and electrical locks to loss of supply and fire-alarm activation. Their functions differ; one general statement about "automatic doors" is insufficient.
  • Resident equipment and assistance. Identify the equipment required for care, communication, repositioning or movement, including hoists and profiling beds. Check nurse-call arrangements and any functions that depend on charging or powered adjustment.
  • Warmth, water and hygiene. Establish how interrupted heating, hot water and other essential services would affect residents. Agree how staff will identify deterioration and escalate concerns, taking individual needs into account.
  • Communications and records. Establish whether staff can contact assistance and access the information needed to provide care when their usual systems are unavailable.

The HIQA handbook specifically addresses power-failure considerations for lighting and certain door arrangements. Those safeguards must be understood in the context of the installed systems. Staff should not improvise by wedging fire doors or changing electrical releases to make movement easier.

Uncertainty should result in a defined action. If management cannot establish how a particular arrangement behaves, competent persons should resolve that question before the contingency plan relies on it.

How do the needs of residents change the plan?

The review should use current information about the residents, rather than an assumed level of independence. A change in mobility, cognition, communication or clinical support can alter the assistance required during a disruption.

For a resident who depends on powered equipment, the question is what happens to that person's care when the normal supply is lost. A device may have an alternative operating arrangement, but its suitability and limits need to be established from the applicable instructions and clinical assessment. The plan should identify who makes those decisions and how staff obtain help.

Oxygen provision illustrates the point. HSE home oxygen guidance identifies the need for emergency backup when a concentrator cannot operate because of a power cut or equipment failure. That guidance concerns home use. A nursing home's arrangements must be agreed through its own clinical and supplier procedures, including the equipment, prescribed treatment and staff competence. Staff should not change oxygen treatment or improvise a connection because an electrical supply has failed.

Powered pressure-relieving mattresses require similar attention to the exact model and instructions. A question about maintaining care during an outage is different from a question about evacuating a resident on the mattress. Phoenix STS's article on evacuation sheets and air-mattress compatibility explains why the complete evacuation arrangement needs evidence. An outage does not justify substituting an unassessed sheet or assuming that a mattress remains suitable for a particular evacuation method.

Relevant information should be available to the staff on duty, including agency staff. Where paper contingency records are needed, management should provide a controlled, current version and protect the personal information of residents. An obsolete dependency list can mislead staff at precisely the point when electronic records are difficult to access.

What evidence supports the backup arrangements?

A record that a generator was serviced is useful, but it does not by itself establish which equipment the generator supplies or how the centre will manage the whole interruption.

Management should seek an explanation that connects the electrical arrangements with the care and fire-safety plan. Which circuits are supported? What interruption occurs while the alternative supply becomes available? Are there essential functions outside those circuits? Who receives a failure indication, and what happens if changeover does not occur?

These questions should be answered by competent persons using the actual installation, design information and appropriate maintenance and testing records. Staff responsible for residents need the operational consequences explained in language they can use. They should not be expected to interpret an electrical diagram during an emergency.

The plan should also address sustaining the alternative supply and obtaining assistance. Access restrictions, contractor availability and delivery arrangements may affect the response. Management should establish which commitments are confirmed and which remain assumptions, with a fallback for arrangements that cannot be relied upon.

There is no single backup duration that this article can prescribe for every nursing home. The period during which a particular system can operate, and the period during which the needs of residents can be met safely, are different questions. Both depend on the circumstances and supporting evidence.

Testing should be planned and controlled. An exercise intended to check preparedness should not interrupt essential resident support. Any physical test affecting critical supplies requires an appropriate plan, competent personnel and arrangements to protect residents throughout.

Do solar panels or additional generators change the position?

A centre with solar panels should establish whether the installation can provide usable electricity during an outage. SEAI explains that a typical grid-connected solar installation disconnects when the grid supply fails. Its January 2026 article concerns homes, but the distinction between electricity generation and a designed backup arrangement is relevant to this management question.

Management should ask the responsible contractor to explain the installed arrangement, its supported loads and its operating limits. The presence of panels or a battery should not be recorded as emergency provision without that evidence.

ESB Networks guidance on standby generators requires appropriate changeover arrangements and Registered Electrical Contractor involvement. It warns against improvised connections into ordinary sockets. A temporary generator proposal therefore needs competent assessment and a safe installation arrangement before it becomes part of the contingency plan.

The same discipline applies when equipment is added or replaced. Management should arrange a review of the affected supply assumptions, so that an equipment upgrade does not leave the emergency plan describing an arrangement that no longer exists.

Can the available staff carry out the plan?

An outage plan should be tested against the staffing and skills available when it might be needed. A procedure that depends on the facilities manager being present may be difficult to use at night unless another person has the necessary information and authority.

Consider the competing tasks. Someone may need to assess residents whose equipment has stopped, while others maintain care, check reported system faults, contact support and manage movement through the building. The plan should make responsibilities clear without assuming that one member of staff can carry out several urgent tasks simultaneously.

Staff should know who coordinates the response, who can authorise escalation and how to reach clinical, electrical and management support. If a nominated person cannot be contacted, the alternative should already be identified.

The HSE's severe-weather guidance for managers includes communication checks, review of vulnerable service users and staffing preparations. For a nursing home, the practical review should examine the effect of delayed relief staff and disrupted access as well as the loss of electricity itself.

Information needs to survive a change of shift. A concise handover should record affected systems, residents requiring additional support, actions already taken and the next decision or review point. Staff coming on duty should not have to reconstruct the situation from several telephone conversations.

The centre's normal emergency arrangements still apply. A problem with routine communications must not become a reason to delay seeking emergency assistance.

When should management escalate or consider relocation?

The plan should identify conditions that require action before safeguards or essential care become inadequate. A decision based only on how long the electricity has been off may overlook a resident whose needs cannot be met from the outset.

Management should agree the relevant decision points with the competent persons and clinical staff involved. These may relate to a failed alternative supply, deterioration in a resident's condition, loss of an essential fire-safety function or the inability to sustain necessary care. The evidence and responsibilities should be recorded, with a clear route for obtaining urgent advice.

Review points should allow time to act. Transport, a suitable receiving location and the assistance needed to move residents may not be available immediately. Waiting until an essential arrangement has already failed can remove options that were available earlier.

Where relocation may be necessary, identify what the proposed destination can actually provide. Space alone does not establish that it can accommodate the care needs, equipment, staffing and accessibility requirements of the residents. Management should confirm the relevant arrangements and how residents, medicines and necessary information would be transferred safely.

The HIQA handbook addresses continued care and accommodation where an evacuation becomes prolonged. Weather and welfare needs form part of that planning. These considerations should inform the contingency arrangements without being confused with the immediate movement required during a fire.

The plan should also address recovery. Before ordinary arrangements resume, the responsible people should establish that affected systems and equipment have returned to the intended condition. Record faults, temporary measures and any further checks required. The return of mains electricity is an event to assess, not evidence that every affected function has recovered correctly.

How can management test the plan safely?

A tabletop exercise can expose unanswered questions without deliberately removing electricity from occupied areas. It should complement the centre's other training and testing arrangements, rather than being treated as proof that equipment will perform.

Consider this hypothetical exercise: normal electricity fails during a winter night shift. Staff receive reports that some equipment is unavailable. The restoration time is uncertain, and the person who normally deals with the electrical installation cannot be reached.

The exercise should require participants to use the centre's actual documents. Ask them to establish:

  1. Which information confirms the fire-safety systems and essential services still available?
  2. Which residents require immediate assessment or additional support?
  3. How will staff communicate and access necessary care information?
  4. Who can explain the backup arrangements and respond to a fault?
  5. What circumstances require escalation or a relocation decision?
  6. What support and receiving arrangements have been confirmed?

Introduce a further difficulty only after the first decisions have been discussed. For example, the expected relief staff may be delayed. That is an exercise assumption, not a claim about the centre or a prediction of a particular weather event.

The value lies in the evidence behind the answers. "The generator should cover that" is an unresolved point until someone can identify the relevant information. "We would move everyone" needs an explanation of the assistance, route, transport and destination on which that response depends.

Keep a short action record identifying the issue, its consequence, the person responsible and the completion evidence required. Where a gap affects a safeguard on which the current plan depends, management should obtain competent advice on interim arrangements.

After corrective work, revisit the affected part of the exercise. A revised document is useful only if staff understand the change and the necessary arrangements are available. Phoenix STS's guidance on tabletop exercises for nursing-home fire safety provides further context for structured discussion and recording outcomes.

What should management complete before winter?

A practical autumn review should leave management with a small set of usable records:

  • a current account of essential equipment and systems, their supply arrangements and any unresolved limitations;
  • resident-specific contingency information agreed with the relevant clinical and equipment providers;
  • clear staff responsibilities, escalation arrangements and accessible contact details;
  • confirmed assistance and relocation arrangements where these form part of the plan;
  • evidence that identified defects and exercise actions have been addressed.

Existing records may already contain much of this information. The task is to establish whether they are consistent, current and usable together. Duplicating them into another large folder will not resolve a missing operational answer.

Start with the most consequential uncertainty. If management cannot establish how an essential function will be maintained, assign the question to the person competent to resolve it and record what can safely be relied upon in the meantime. Continue until the plan describes arrangements that the centre can demonstrate and staff can explain.

Phoenix STS provides healthcare evacuation planning and nursing-home fire risk assessment. These can help management examine the relationship between residents, the building and the proposed response, with electrical, clinical and equipment questions referred to the relevant competent persons. Contact Phoenix STS to discuss the scope of a review.

Sources

Image: Enclosed diesel generator in Tallinn, Estonia. Photograph: Dmitry G, SDMO diesel-generator in Ülemiste / Wikimedia Commons (CC BY-SA 3.0). Resized and cropped for display; image adaptations retain the same licence.

Important note

This article is provided for general information only. It is not legal advice and does not replace a site-specific fire safety, health and safety, training or professional assessment for a particular premises, organisation or care setting.